The new turbines ordered for the power plant at Dhekelia may not arrive until 2030, officials of the Electricity Authority of Cyprus (EAC) told MPs on Monday.
EAC board chairman Giorgos Petrou said that, after a tender, the contract – worth €140 million – for the three turbines was awarded to Siemens.
Initially the delivery timeline was two-and-a-half years from the present day – placing it in mid-2028.
But two